Millard E. Tydings Memorial Bridge Repairs
I-95 over the Susquehanna River
Work involves replacing expansion joints and portions of the concrete deck, drainage system installation, and miscellaneous cleaning and painting.
Northbound Closures (April through July) - Sunday 11 p.m. through Friday 5 a.m. - continuous single lane closure.
Northbound Closures (July through September) - Sunday 11 p.m. through Friday 5 a.m. - continuous single lane closure. Monday through Thursday from 9 p.m. to 6 a.m. the following morning - double lane closure.
Southbound Closures (October through December) - Sunday 11 p.m. through Friday 5 a.m. - continuous single lane closure. Monday through Thursday from 8 p.m. to 5 a.m. the following morning - double lane closure.
No lane closures will be permitted the day before, day of, and the day after major holidays.
|